Construction Timeline

Based on Moss Development schedule — Demo to closeout in 3 months (Apr 1 → Jun 30)

Per Moss Schedule

Early July 2026

Permit approved Mar 2, no delays, no major change orders

Realistic (+2 wk buffer)

Mid-July 2026

Minor delays in inspections or material delivery

If permit delayed / change orders

Aug–Sep 2026

Permit pushback, scope changes, trade scheduling conflicts, will also need bail money

Taking risks and softening corners

Early June 2026

If we take risks ordering mechanical ASAP, we can reduce the probability of waiting on items. Moss acknowledged that we can make up some build time in some areas.

Milestone Timeline

Pre Construction

Tender CloseFeb 26, 2026
Moss DevelopmentBids collected
Building Permit ExpectedMar 2, 2026
City of St. John'sCritical gate
Contract AwardMar 6, 2026
Moss DevelopmentGC contract signed
Shop DrawingsMar 9, 2026
Moss / TradesDetailed trade drawings
Material PurchaseMar 23, 2026
VariousLong-lead items ordered
Site MobilizationMar 30, 2026
Moss DevelopmentEquipment on site

Construction

DemolitionApr 1, 2026
Moss DevelopmentStrip-out of existing space
FramingApr 15, 2026
Moss DevelopmentWalls, partitions, structure
Rough-in (Mech/Elec/Plumb)Apr 22, 2026
NF HVAC / TradesCritical path
Fire ProofingApr 28, 2026
INS Solutions$27,000 — ceiling fire rating
Sprinkler InstallMay 4, 2026
Martin's Fire Safety$7,050 + HST
Inspections (Rough-in)May 11, 2026
City / FireMust pass before closing walls
DrywallMay 12, 2026
Moss / SubAfter inspection approval
Plaster / FinishMay 18, 2026
Moss / SubSkim coat and finish
PaintMay 25, 2026
Moss / Sub
CeilingsMay 28, 2026
Moss / SubDrop ceiling and finishing
Flooring InstallJun 3, 2026
Urban Flooring$3,690 + HST
Millwork InstallJun 9, 2026
Moss / CustomBar, built-ins, trim
Fixture InstallJun 10, 2026
VariousPlumbing & light fixtures
Kitchen Equipment InstallJun 16, 2026
Self / SuppliersMost equipment on hand
Final CleaningJun 18, 2026
TBDConstruction clean

Commissioning

Systems BalancingJun 22, 2026
NF HVACHVAC/ventilation testing
Deficiency ReviewJun 24, 2026
Moss / OwnerWalkthrough and punch list
Final InspectionJun 29, 2026
City / Fire / HealthAll regulatory sign-offs
Project CloseoutJun 30, 2026
Moss DevelopmentHandover to owner

Construction Bid Breakdown

Scope
Demolition
Subcontractor
Moss
Quote
$90,000
Scope
Mechanical (HVAC/Plumbing)
Subcontractor
NF HVAC
Quote
$294,750
Scope
Electrical
Subcontractor
NF HVAC
Quote
$163,750
Scope
Fire Suppression
Subcontractor
Martin's Fire Safety
Quote
$7,050
Scope
Fire Proofing (Ceiling)
Subcontractor
INS Solutions
Quote
$27,000
Scope
Doors and Frames
Subcontractor
Apex
Quote
$15,305
Scope
Flooring
Subcontractor
Urban Flooring
Quote
$3,690
Scope
New Construction
Subcontractor
Moss
Quote
$187,879
Scope
Walk-in Cooler (Optional)
Subcontractor
Whitten Agencies
Quote
$18,650

Construction Cost Summary

Subtotal (Subs/Suppliers)$808,074
Moss Overhead (5%)$40,404
Moss Markup (7%)$56,565
Client Total (Pre-HST)$905,043
HST (15%)$135,756
Client Total Incl. HST$1,040,799
Change Order Allowance (10%)$90,504

Key Observations